Commercial Operation of Hakedi Wind Farm


(2017-06-20) Click:2990

The first unit of Hakedi Wind Farm, located in Yuxi City, 222 km from Kunming of Yunnan Province, was put into commercial operation on June 9, 2017. 

Started in January 2016, this farm is the first wind project invested by Wuling in Yunan Province, with total installed capacity of 50 MW, 25 units of 2 MW each, and annual output of 119.68 GWh. All the other units are scheduled to be put into operation by the end of June 2017.

The commercial operation of this farm is a milestone of Wuling's entrance into the Southern China clean energy market, which provides guidance for the wind power projects development in the neighboring provinces around Yunan Province.