Longshan Wind Power Plant Begins Operation


(2018-05-08) Click:2707

The first unit of Longshan Wind Power Plant was smoothly connected to grid, and began power production on April 25, 2018.
Located in Lianyuan, Hunan, this Plant is designed to install 25 wind turbine units (2MW each) supplied by SANY, with total installed capacity of 49.9MW and the designed yearly output of 108.7 GWh. The height of its tower is 80 meters, with the hub height of 85 meters, and the rotor diameter of 115 meters.
The plant began construction on Feb. 26, 2017, and all the units are expected to be put into operation in August this year.